A Proposal for
na2air
Hair Dryer Fragrance Capsule and Retail Kit
na2air & the Engineering Validation Engagement
na2air is a Saudi Arabia based product company founded by Abdulaziz Alnabulsi and Dr. Abdulilah Alnabulsi, both engineers and joint holders of the product intellectual property. The product is RoRoCap, a small disposable fragrance capsule that attaches to the outlet grill of a hair dryer and releases scent into the hair through the warm airflow during normal use.
The capsule is an annular ring, 21mm diameter by 16.5mm height, with perforated intake and exhaust walls and an internal cotton matrix soaked in fragrance oil. It attaches by magnetic fixation: a ferrous washer is press-fit into the capsule base and snaps onto a ring magnet. The product works across hair dryer brands using the magnet directly on metal grills, or a plastic fixator adapter on non-metallic grills. The retail kit contains 3 sealed scented capsules, 1 ring magnet, 1 grill fixator adapter, and a printed user manual, in a retail box with protective inserts.
na2air holds granted patents in the United States, the United Kingdom, the European Patent Office (Unitary Patent), and Singapore. A first pilot run of approximately 1,000 units was produced outside China for market testing, in injection-moulded plastic. Those unit costs were high and are not treated as a useful benchmark for a China-based commercial run. The company has full 2D engineering drawings with tolerances, a bill of materials, a user manual, CAD, and physical samples available. The fragrance oil and chemical formula are owned by na2air and are supplied directly to the factory for filling.
na2air has approached C2W and Shield Works to scale production, to evaluate the existing plastic architecture against a proposed pressed metal capsule design, and to establish a real factory-door unit cost for an initial 5,000 kit validation run, ahead of a 25,000 unit per year forecast. This proposal covers Stage 1 of that program, titled Phase 1, Engineering Validation, following the discovery call held on 15 June 2026 and the NNN agreement currently being put in place between our teams.
This proposal is marked provisional in that the figures in Section 5 are indicative and firm up through Phase 1. The Phase 1 scope and fee set out below are firm. The first technical session, the Engineering Kickoff Workshop in Deliverable 1, aligns the work against the real technical priorities, principally the thermal performance question and the plastic versus metal material decision, before engineering work begins. See Section 10 for the sequence.
Our Preliminary Read on the Product
Ahead of Phase 1 engagement, our team has reviewed the brief, the intake form, the discovery call notes, the bill of materials, the engineering drawings, and the user manual. CAD and STEP files will be reviewed on receipt. The following is not the full Phase 1 output, but it is the position from which our engineering work will start.
There is a contradiction in the supplied documentation that must be resolved before any material is selected or any unit cost is quoted, and it is the single most important item in Phase 1.
The brief and project summary state that the capsule, its internal matrix, and its seals must withstand operating temperatures up to 200 degrees C and airflow up to 210 km/h without deformation, outgassing, or leakage. The user manual supplied with the same product instructs the end user not to exceed 110 degrees C. The engineering drawings specify PC-ABS as the capsule material, which softens well below either figure, while the brief separately refers to a Nylon 66 GF30 pilot build.
These positions cannot all hold. The true operating temperature the product must survive in normal use drives everything downstream: whether a high-temperature engineering plastic is necessary at all, whether PC-ABS is adequate, whether the pressed metal upgrade is justified on performance grounds or only on cost and perception, the choice of cotton matrix and fragrance carrier, and the sealing method. Phase 1 carries this as a standalone engineering workstream. We will establish the real thermal and airflow envelope at the grill, define the temperature the enclosure and seals must be specified to, and lock the material question against that number rather than against an assumption.
Program Targets
The following reflects current working assumptions drawn from the intake form, the brief, and the discovery call notes. The figures will be reconciled and validated through Phase 1.
| Item | Detail |
|---|---|
| Prototype Quantity | Approximately 250 units for design and process validation |
| First Production Run | 5,000 retail kits, positioned as a supply chain activation and process validation run |
| Annual Volume Forecast | Approximately 25,000 units per year |
| Target Unit Price | $1 to $2 USD long-term at scaled volume, confirmed by na2air as a long-term optimisation target rather than a constraint on the first run; validated through the Phase 1 Indicative Quotation |
| Target Timeline | 2 to 3 months for the same plastic material with new packaging and fixator, or 3 to 5 months for the metal upgrade (indicative, to be confirmed in the Development Roadmap) |
| Target Markets | United States and Europe primary, with further jurisdictions to follow |
| Funding Status | Secured |
Six Phase 1 Deliverables
Phase 1, Engineering Validation is the first paid engagement in the na2air development program. The work is engineering-led: an independent audit of the existing drawings, CAD, and BOM, a focused engineering workstream on the thermal performance and material question, a comparative DFM evaluation of the plastic and metal architectures, an assessment of the existing tooling, supplier engineering engagement with indicative pricing, certification and logistics scoping, and a Development Roadmap that consolidates the output into a costed phase-by-phase pathway to qualified mass production.
Duration: approximately 4–6 working weeks from confirmation.
Phase 1 consists of the following six deliverables.
The 25 to 35 page consolidating document that carries the Phase 1 engineering output forward into Phase 2 and through to qualified mass production. This is the full Route to Market Plan for na2air.
The Development Roadmap will include:
- Phase timelines and phase management costs across the full development program.
- Shield Works resource allocations and core deliverables across sampling, development, design optimisation (full DFM, DFA, DFX), prototyping, pilot run manufacture, mass production, and scaled production.
- Consolidated written output of the Phase 1 engineering work, including the audit findings, the thermal and material workstream output, and the DFX assessment.
- Component-level bill of materials with material specifications and qualified supplier direction, for both the plastic and metal paths.
- Mechanical and DFM plan for the capsule, fixator, washer, and kit components, with the recommended material path and tooling strategy.
- Capsule filling, dosing, and sealing process plan, and the retail kit assembly plan.
- Fragrance supply plan with the recommended source and benchmarking outcome.
- Certification pathway per target market, with the testing route and indicative cost direction.
- Logistics and fulfilment plan, including Amazon FBA prep, barcoding, and paperwork, and warehousing options in China.
- Prototyping and iteration plan with validation gates.
- Tooling strategy and indicative tooling investment budget, including the assessment of the existing pilot tooling.
- Pilot run manufacture plan with QC gating criteria, mass production pathway, packaging direction, and a risk register with mitigations and owner assignments.
Note: Phase 1 is the first phase of the na2air development program. Phase 2 and subsequent development, tooling, certification, and production work is scoped and costed within the Development Roadmap for na2air's approval before any execution begins.
Indicative Development Envelope Preview
The figures below are preliminary ranges produced from our initial review and our experience with multi-component consumer products manufactured in China. They are shared ahead of the Phase 1 Indicative Quotation so the shape of the investment is clear from the outset. They will be firmed up, detailed, and locked against specific supplier quotes in the Phase 1 output. The ranges below reflect the plastic architecture as the base case; the metal architecture is evaluated in parallel and carries its own tooling profile, confirmed in Phase 1.
| Stage | Scope | Timeline | Indicative fee |
|---|---|---|---|
| Engineering refinement and DFM | Audit, thermal and material resolution, DFM on both paths, supplier drawings | 4 to 6 weeks | $6,000 to $10,000 |
| Prototype build | First validation prototypes in the confirmed material, approximately 250 units | 3 to 5 weeks | $5,000 to $9,000 |
| Prototype iteration (likely) | Second iteration on seal, fit, and any DFM-driven design changes | 2 to 4 weeks | $3,000 to $6,000 |
| Injection mould tooling (plastic path) | Multi-cavity tooling for base, lid, and fixator | 6 to 10 weeks | $12,000 to $28,000 |
| Metal forming tooling and cutting die (metal path, if selected) | Forming mould for the capsule containers and cutting die, in place of injection tooling | 6 to 10 weeks | $10,000 to $24,000 |
| Filling and assembly line setup | Cotton insertion, oil dosing, sealing, and retail kit assembly setup | 3 to 5 weeks | $4,000 to $9,000 |
| Pilot run (5,000 kits) | Validation production run, real unit economics baseline, marketing samples | 3 to 4 weeks | Per Phase 1 unit cost |
| Development total (before mass production) | Indicative envelope, single material path tooled, one prototype iteration | approx. 2 to 5 months | $30,000 to $62,000 |
Ranges assume a single material path is tooled following the Phase 1 recommendation, plus a single prototype iteration. The envelope excludes the 5,000 kit pilot production cost, fragrance oil (client-supplied), sample shipping, and any third-party testing or certification fees, which are addressed separately in Section 6. The metal and plastic tooling lines are alternatives, not additive; only the selected path is tooled.
| Risk | Likelihood | Impact | Primary mitigation |
|---|---|---|---|
| Real operating temperature differs from the 200 degrees C brief figure, changing material selection and cost | High | High | Thermal workstream in Phase 1 establishes the true envelope and locks material against it before tooling |
| Specified PC-ABS or chosen plastic deforms or outgasses at the real grill temperature | Medium | High | Material grade confirmed against the validated thermal envelope; high-temperature grades or metal path evaluated |
| Friction-fit seal leaks fragrance oil under heat and airflow | Medium | Medium | Sealing assessed in DFM; sealing method validated at prototype stage in Phase 2 |
| Existing pilot-run tooling not usable or transferable to China | Medium | Medium | Tooling assessment in Phase 1 confirms reuse, transfer, or replacement before budget is committed |
| Certification requirements across US, EU, and further markets affect design, labelling, or timeline | Medium | Medium | Certification pathway scoped per market in Phase 1; testing routed through accredited partners |
| $1 to $2 target unit cost not achievable at 5,000 unit volume | Medium | Low | Client has confirmed the target is long-term and scaled; Phase 1 establishes the real first-run baseline and the trajectory to target |
Indicative unit pricing is not included at this stage. The material decision and the resolved thermal envelope materially affect per-unit cost and will not be locked until the Phase 1 work is complete. Unit pricing at multiple volume tiers, for both material paths, will be delivered in the Phase 1 Supplier Engineering Shortlist and Indicative Quotation.
What Sits Outside Phase 1
The Phase 1 fee covers all six deliverables in Section 4, including the engineering work, the audit, the thermal and material workstream, the DFX assessment, supplier engagement, indicative quotation, certification and logistics scoping, and the Development Roadmap. The following are excluded and would be scoped and costed within the Development Roadmap itself, or addressed through external partners coordinated by Shield Works.
once a supplier set is confirmed and production begins, C2W and Shield Works operate as na2air's manufacturing partner. na2air receives a single unit cost per retail kit that covers goods, capsule filling and assembly, quality control, supplier management, packaging, and logistics coordination. These are not billed as separate service fees. The Phase 1 Supplier Engineering Shortlist and Indicative Quotation is designed to establish those unit costs with confidence before any production commitment is made.
Phase 1 Payment
| Stage | Fee | Payment trigger |
|---|---|---|
| Phase 1, Engineering Validation | $7,500 USD | Payable in full on project confirmation |
How We Keep Phase 1 Honest
Why C2W and Shield Works
From Acceptance to Phase 1 Delivery
This proposal is non-binding at this stage and is intended to give na2air clarity on cost, structure, and what Phase 1 will actually produce. If you are happy with the direction, let us know and we will issue the invoice and get the Engineering Kickoff Workshop scheduled.
Best regards,
Mark Jacobs
CEO, C2W Group / Shield Works
June 2026